Mar 19, 2026

Who’s Financing Phoenix’s Data Center Boom?

$10.3B
Total Identified Debt
135
Data Center Facilities
59
Unique Lenders
2.4 GW
Deployed Capacity
135 Data Centers in Maricopa County — 2.4 GW Deployed
Color = stage. Size = power capacity (MW). Click any marker for details. Source: DataCenterMap.com + CBRE + Mordor Intelligence.

Phoenix is the fastest-growing data center market in the United States. Total deployed capacity across all facility types in Maricopa County reached an estimated 2.1 GW in 2025, with another 300 MW under construction and a planned pipeline of 2,700+ MW. Statewide, the figures are even larger: 2.4 GW deployed, 3,800+ MW planned. Of the operational capacity, roughly 600 MW is colocation and wholesale (per CBRE); the rest is hyperscaler-owned (Apple, Google, Microsoft, Meta) and enterprise. According to Data Center Dynamics, Arizona topped all states with $41 billion in data center loans committed during 2025.

We mapped 135 data center facilities in Maricopa County across every layer of the capital stack: property-level mortgage filings ($4.0B), syndicated project finance ($5.5B), CMBS ($735M), UCC filings, and corporate credit facilities ($50B+ accessible). The result: $10.3 billion in identified data center debt spread across 59 unique lenders, from Wall Street to Japanese megabanks to Korean development agencies. This analysis names every name.

Three Layers of Capital

Data center financing does not follow the traditional CRE playbook. Rather than one mortgage per property, capital flows through three distinct layers:

LayerAmountDealsDescription
Property Mortgages$4.0B77Recorded against individual parcels. Wells Fargo, BofA, BMO dominate.
Syndicated Project Finance$5.5B6Multi-bank facilities for specific campuses. MUFG, Sumitomo Mitsui lead.
CMBS / ABS$0.7B1Vantage VDCM 2025-AZ. QTS also tapping ABS ($510M, Mar 2026).

Above these sits a fourth layer: corporate revolvers and portfolio facilities totaling $50 billion or more across the parent companies operating in Maricopa County. Blackstone’s CyrusOne alone carries $28 billion in syndicated capacity. The largest Phoenix data centers (Compass 350 MW, Aligned 180 MW, CyrusOne 130 MW) have zero property-level debt because their financing lives entirely at the corporate level.

UCC filings confirm the linkage: Aligned’s Phoenix, Chandler, and Glendale campuses all show Toronto Dominion (Texas) LLC as collateral agent. Novva’s planned Mesa campus shows JPMorgan Chase and GLAS Americas. QTS Glendale shows both Citibank and Goldman Sachs as secured parties across 16 separate SPVs.

Layer 1: Property-Level Mortgages ($4.0B)

Data Center Lending by Vintage
Mortgage originations on matched data center properties in Maricopa County

Big Banks Dominate Data Center Finance

Six banks with total assets exceeding $250 billion account for 73% of property-level mortgage volume in Maricopa County. Wells Fargo leads with $1.68 billion across six properties, followed by Bank of America at $578 million across six properties.

This concentration reflects the sheer scale of data center financing. A single hyperscale facility can require $300 million to $1 billion in debt. Community and regional banks rarely have the balance sheet capacity, driving borrowers to the largest national lenders and syndicated loan desks.

Lending Volume by Lender Type
Big Bank = $250B+ assets, Regional = $10B-250B, Community = under $10B

The Top Properties

The ten largest data center loans in Maricopa County represent $3.9 billion in exposure. Iron Mountain’s AZP-2 campus on East Van Buren Street leads at $604 million, financed entirely by Wells Fargo. STACK Infrastructure’s planned campus in Goodyear secured $469 million from Bank of America before breaking ground.

Iron Mountain AZP-2
4802 E Van Buren St, Phoenix • Wells Fargo • 547,000 SF • 48 MW
$604M
11:11 Systems Scottsdale
7499 E Paradise Ln • BMO Bank, PNC • 102,400 SF
$537M
STACK Infrastructure PHX01A
W Lower Buckeye Rd, Goodyear • Bank of America • Planned
$469M
LexisNexis Scottsdale
Scottsdale • Wells Fargo
$390M
Vantage AZ13 Phoenix
Goodyear • Wells Fargo • CMBS: VDCM 2025-AZ
$385M
DataBank PHX2 Sky Harbor
Phoenix • First Citizens, Wells Fargo • Multi-lender
$356M
Stream DC Goodyear Campus
Goodyear • GLAS Americas • 6 buildings
$345M

Layer 2: Syndicated Project Finance ($5.5B)

Atrium’s syndicated loan database reveals six Arizona-specific data center facilities totaling $5.5 billion. These are syndicated project finance deals arranged by global banks, with MUFG and Sumitomo Mitsui serving as administrative agents on the largest transactions. The lender syndicate is strikingly international: Korean Development Bank, Norinchukin, CaixaBank, DBS, OCBC, Bayerische Landesbank, and Commerzbank all participate.

BorrowerAmountAdmin AgentLenders
QTS Glendale I DC1$2.10BMUFG Bank17
QTS Phoenix II DC2$1.28BSumitomo Mitsui12
STACK PHX01A-C$824MSumitomo Mitsui13
Vantage AZ11$600MWells Fargo5
Iron Mountain AZ3$393MCredit Agricole3
Brookfield Phoenix DC$300MWells Fargo4

Layer 3: CMBS / ABS ($735M and Growing)

Only one securitized data center loan surfaces in Maricopa County: the Vantage AZ11-13 campus at 45 South Bullard Avenue in Goodyear. The $735 million CMBS loan (deal: VDCM 2025-AZ) was originated in mid-2025 against a 495,654 square-foot facility at a 5.07% note rate. QTS has also tapped ABS markets, closing a $510M refi in March 2026 for its Phoenix and Richmond campuses.

The scarcity of CMBS exposure relative to the $5.5B in syndicated lending and $4.0B in mortgage filings is the finding. Data center financing remains overwhelmingly on bank balance sheets, in syndicated facilities, or in private credit vehicles. Bank regulators, not rating agencies, bear primary surveillance responsibility for the sector’s rapid growth.

The bank concentration is the story. Of $10.3 billion in identified Maricopa County data center debt, only $735M is securitized. The rest sits on bank balance sheets via mortgages and syndicated facilities. But the lender base is far more international than traditional CRE: Japanese megabanks, Korean development institutions, and European banks from France, Germany, Spain, and Italy all have material exposure. If Phoenix data centers stumble, the ripple extends to Tokyo, Seoul, and Frankfurt.

Non-Bank Capital: Private Credit Fills the Gaps

Non-bank lenders account for $632 million, or 15% of recorded mortgage volume. We resolved the two largest to their ultimate sponsors:

Fund VI CRE Lender-Thistle LLC ($92M) is a lending vehicle of Pennybacker Capital, an Austin-based private equity firm focused on commercial real estate. The $91.95 million mortgage (dated May 3, 2024) was originated to ME PHX Tech Campus LLC, a Delaware entity developing the Menlo Digital MD-PHX1 campus at 4801-4811 E Thistle Landing Drive. Menlo Equities, a 30-year Silicon Valley PE firm ($9.7B cumulative AUM), is building a 5-building, 38-acre, 257 MW hyperscale campus on the former Thistle Landing office park. First shells deliver Q2 2026. A collateral assignment recorded July 24, 2024 shows Simmons Bank (an Arkansas state bank) as assignee — Fund VI pledged the deed of trust to Simmons as security for a separate $50.5 million loan. Simmons does not hold the underlying mortgage but has a security interest in it.

GLAS Americas LLC ($345M) is not a lender but an independent loan agency (Global Loan Agency Services) serving as collateral agent on a syndicated facility for Stream Data Centers’ 157-acre, 280 MW Goodyear campus. Apollo-managed funds acquired a majority stake in Stream in 2025. The actual lending syndicate behind the $345M facility is not identified in the county recording.

The remaining non-bank names resolve to familiar institutions: IXIS Real Estate Capital is the pre-2007 brand of Natixis (French bank, $71M filing). Column Financial was Credit Suisse’s CMBS conduit, now absorbed by UBS. Toronto Dominion (Texas) LLC is simply TD Bank’s U.S. lending vehicle.

The Unified View: $10.3B Across 59 Lenders

Combining mortgage filings, syndicated loan allocations (estimated by role), and CMBS origination, we can estimate each lender’s total Maricopa County data center exposure. The result reshapes the picture: the dominant lender holds $2.4B across every capital layer, but Japanese megabanks collectively hold $1.5B, and European banks another $1.7B.

The full lender-by-lender breakdown is available exclusively to Atrium subscribers.
Every lender named. Every dollar traced. Every syndicate mapped.
Request a Demo
Top 20 Lenders: Unified Estimated Exposure
Stacked by source: mortgage filings (gold) + syndicated loans (blue) + CMBS (red)
Exposure by Lender Nationality
Phoenix data center debt extends to Tokyo, Seoul, Madrid, and Frankfurt

The Dominant Lender: $2.4B Across Every Layer

One bank appears in every layer of the capital stack: $1.68B in property mortgages across 6 properties, $526M in syndicated facilities, and an estimated $245M in CMBS origination. UCC filings confirm this lender as secured party on multiple Vantage campuses. Total estimated exposure: $2.4 billion. Atrium subscribers can see which bank it is.

The Japanese Connection

Japanese banks hold an estimated $1.5 billion in Maricopa County data center exposure, entirely through syndicated project finance. Three megabanks lead the largest deals, with regional Japanese institutions participating. None of these banks appear in property mortgage records.

Korean and European Banks

Four Korean institutions collectively hold an estimated $400+ million. European banks from Spain, France, the Netherlands, Italy, and Germany total an estimated $1.5 billion. This international syndicate reflects data center project finance’s appeal: long-duration, high-credit-quality tenants (hyperscalers), and infrastructure-like cash flows.

The Pipeline: $60B+ in Announced Projects

The pace of new announcements in late 2025 and early 2026 has been extraordinary. Recent major projects in Maricopa County alone:

Aligned Data Centers (BlackRock/GIP Acquisition)
Glendale • 72 MW first building • 5 GW total portfolio • Groundbreaking Apr 2025
$40B
Hassayampa Ranch (ALC / Chamath Palihapitiya)
Tonopah • 2,100 acres • 1-1.5 GW • Rezoning approved Dec 2025
$25B
Novva Data Centers
Mesa • 160 acres • 300 MW • Phase 1 late 2026
$3B
QTS PHX3 (Blackstone)
Glendale • 400 acres • 750 MW • 16 buildings, 3M SF
$2.5B+
EdgeCore Mesa Campus
Mesa • 450 MW at full build • 3.1M SF • $1.9B green loan
$1.9B
Project Baccara / Takanock
Surprise • 700 MW gas plant + 1M SF DC • ACC approved Feb 2026
TBD

According to APS’s own rate case testimony (Docket E-01345A-25-0105, March 2026), the utility is contractually committed to serving 3,296 MW of data center load by end of 2028 and is actively negotiating an additional 16,908 MW after 2028. Combined, that is 20,204 MW — more than 200% of Arizona’s current 8,200 MW system peak. Each new facility is likely 200 MW or larger. If just 1,000 MW of the committed capacity becomes stranded after 15-year contracts expire, APS estimates $75 million per year in stranded costs. Applied to the full negotiation pipeline: $460 million per year.

The Potter/Reynolds-Madsen testimony (same docket) reveals APS’s proposed subscription model: 1.2 GW of initial guaranteed capacity, with financial security requirements of $750 million per 100 MW of requested service. Subscribers must agree to long-term bilateral contracts with fixed and variable charges. The testimony warns that “a downturn in the tech sector or a facility closure could leave existing ratepayers to cover billions of dollars of infrastructure built solely to serve a single, large load.” The potential rate increase to fund data center infrastructure projects: up to 19%.

The Regulatory Headwinds

Governor Hobbs has called for ending Arizona’s 10-year data center sales tax exemption, arguing it has served its purpose. The incentive costs the state approximately $38 million per year in foregone revenue. Chandler City Council unanimously rejected a data center rezoning request after public backlash. A penny-per-gallon fee on data center water use has been proposed. The "No Desert Data Center Coalition" is actively organizing against new projects.

The bigger constraint is power. Phoenix has 1,300 MW under construction and nearly 4,700 MW planned. Utility backlogs and grid capacity, not water or permitting, are now the binding constraint on new supply.

For bank lenders, the question is whether the current construction pipeline can be absorbed by tenant demand. Supply is growing faster than at any point in the sector’s history, and tenant credit is heavily concentrated in four hyperscalers (Google, Meta, Microsoft, Amazon) who collectively accounted for 73% of new leasing in 2025.

What we’re watching: This analysis covers only Maricopa County. With full national coverage, the same methodology would map 4,296 data centers across all 50 states. Virginia alone (668 facilities, including Data Center Alley in Ashburn) would likely double the total exposure. When that data lands, we will publish the full national report.

Risk 1: The Power Grid Is the Binding Constraint

APS currently serves approximately 350 MW of data center load. But 4,000 MW of XHLF (Extra High Load Factor) customers are in construction or coming online, with another 10,000 MW in the queue. APS has publicly stated: “We do not have the energy and transmission infrastructure to support the amount of energy that’s being requested of us.” Data centers accounted for 94% of APS demand growth from 2023 to 2025.

APS has 16,000 MW of data center demand in its interconnection pipeline. To put that in perspective, 16 GW is roughly the electricity consumption of 12 million homes.

Power Pipeline by Utility Territory
Megawatts of data center capacity by grid territory

The Potter/Reynolds-Madsen testimony reveals APS’s proposed subscription model: 1.2 GW of initial guaranteed capacity, with financial security requirements of $750 million per 100 MW of requested service. Subscribers must agree to long-term bilateral contracts with fixed and variable charges. The potential rate increase to fund data center infrastructure projects: up to 19%.

SRP needs to double its generation capacity within 10 years. APS has proposed building a 2 GW gas plant (Desert Sun) under a subscription model where data centers finance their own capacity. Meanwhile, APS’s 2025 rate case proposes a 45% rate increase for XHLF data center customers. If approved, this directly impacts operating costs for every facility in APS territory.

The lender risk: If APS cannot deliver power on the timeline operators need, construction-financed facilities sit idle. The Vantage AZ11 syndicated loan ($600M) matures March 31, 2026. Brookfield’s Phoenix DC revolver ($500M) matures December 2026. That’s $1.1B in data center debt maturing this year in a market where the utility says it cannot keep up with demand.

Risk 2: The Maturity Wall

Syndicated Loan Maturity Schedule
Red = 2026 (urgent), Orange = 2027-2028, Green = 2029+

Risk 3: Water in a Desert

The industry has largely solved the water problem through engineering. Nearly every facility built since 2023 uses air-cooled or closed-loop zero-water cooling. But the legacy facilities and the sheer scale of the pipeline still matter.

OperatorLocationCoolingWater Use
MetaMesaEvaporative456M gal/yr
MicrosoftGoodyearBldgs 1-3 evaporative; 4-5 air56M gal/yr
TractBuckeyeUnspecified652M gal/yr cap
GoogleMesa100% air-cooled~Zero
QTSGlendaleZero-water (refrigerant loop)~Zero
CompassGoodyearAir-cooled (Kyoto wheel)~Zero
VantageGoodyearClosed-loop, air-cooled~Zero
EdgeCoreMesaAir-cooled (WUE <0.01)~Zero
NovvaMesaWater-free air-cooling~Zero
CyrusOneChandlerZero-water (air-cooled chiller)180K gal/yr
StreamGoodyearAir-cooled, closed-loop~Zero
AlignedPhoenixDelta3 air + liquid coolingNear-zero
BaccaraSurpriseClosed-loop, air-cooled≤33M gal/yr

Four cities have enacted data center water regulations. Chandler was first in 2015: 115 gallons per 1,000 SF per day. Mesa caps large users at 330 acre-feet per year and has required developers to bring their own water (Meta purchased Gila River credits; large users have contributed 7,800 acre-feet to the city). Phoenix adopted a Large Water User Ordinance in 2024. Goodyear negotiates case-by-case (Microsoft’s $36M wastewater plant contribution).

The Ceres Foundation projects Phoenix-area data center water consumption will grow from ~385 million gallons per year today to 3.7 billion gallons within six years. But the bigger risk is indirect: the electricity to power these facilities requires its own water. Natural gas power generation consumes roughly 2,800 gallons per MWh. As APS builds gas plants to serve data center load, total water impact could be 5-10x the direct cooling usage.

Risk 4: Regulatory and Political

Governor Hobbs has called for ending Arizona’s 10-year data center sales tax exemption, arguing it has served its purpose. The incentive costs the state approximately $38 million per year in foregone revenue. The ACC opened a formal data center inquiry (Docket E-00000A-25-0069) in April 2025 to ensure infrastructure costs are not shifted to residential ratepayers. APS’s proposed 45% XHLF rate increase (Docket E-01345A-25-0105) is pending. Chandler unanimously rejected a rezoning request after public backlash. The “No Desert Data Center Coalition” is actively organizing.

The bigger constraint is power. Phoenix has 1,300 MW under construction and nearly 4,700 MW planned. Utility backlogs and grid capacity, not water or permitting, are now the binding constraint on new supply.

The Attorney General has challenged the ACC’s approval of Project Blue (a 286 MW data center in Tucson), filing an appeal in January 2026 seeking to vacate the decision. If successful, this could set a precedent that slows approvals statewide.

For bank lenders, the question is whether the current construction pipeline can be absorbed by tenant demand. Supply is growing faster than at any point in the sector’s history, and tenant credit is heavily concentrated in four hyperscalers (Google, Meta, Microsoft, Amazon) who collectively accounted for 73% of new leasing in 2025.

Explore the Full Dataset

$10.3B in identified debt across three capital layers, 59 unique lenders from 12 countries.

Lender names redacted in the public version. Request a demo for the full report with all 59 lenders identified.

Property Mortgages
$4.0B
77 filings, 45 properties
Syndicated Loans
$5.5B
6 AZ-specific project deals
CMBS / ABS
$735M
Vantage VDCM 2025-AZ
Corporate Facilities
$50B+
Parent-level, accessible to AZ
Syndicated Project Finance Deals
Arizona-specific data center facilities from Atrium's syndicated loan database. Amounts and dates verified against database.
BorrowerAmountDateAdmin AgentLendersPurpose
QTS Glendale I DC1 LLC$2.10BMay 2025MUFG Bank17General Purpose
QTS Phoenix II DC2 LLC$1.28BApr 2024Sumitomo Mitsui12Project Finance
STACK PHX01A-C Holdings$824MJul 2024Sumitomo Mitsui13Project Finance
Vantage Data Centers AZ11$600MMar 2023Wells Fargo5Real Estate
Iron Mountain DC Arizona 3$393MMar 2025Credit Agricole3General Purpose
Phoenix DC Intermediate (Brookfield)$300MJan 2024Wells Fargo4General Purpose
Mortgage Origination by Vintage
Annual property-level mortgage volume on data center parcels
Mortgage Volume by Lender Type
Property-level mortgages only. Syndicated shown separately above.
Top 15 Mortgage Lenders by Volume
Property-level mortgages only (excludes syndicated allocations)
Lender Type Breakdown
Classification of all resolved lenders by institution type
Lender TypeTotal VolumeFilingsLendersAvg Per Filing
Big Bank $3.39B 32 6 $106M
Non-Bank / Private Credit $908M 25 20 $36M
Regional Bank $299M 10 5 $30M
Community Bank $52M 10 5 $5M
All Lenders: Unified Estimated Exposure
Combines mortgage filings, estimated syndicated allocations (by role), and CMBS origination. Click to sort, filter by type.
# Lender Type Ticker Filings Properties Total Volume Assets

Methodology

Data center facility locations and metadata from DataCenterMap.com. All financing data, entity resolution, and lender exposure analysis by Atrium. Market capacity estimates reference CBRE and Mordor Intelligence. Regulatory filings sourced from the Arizona Corporation Commission eDocket. Water usage data compiled from city agreements, operator disclosures, and the Ceres Foundation’s “Drained by Data” report (September 2025). Power pipeline figures from operator announcements, APS and SRP disclosures, and ACC filings.

Syndicated loan lender allocations are estimates based on standard market conventions and lender role hierarchy. Actual allocations are not publicly available. This analysis covers Maricopa County only; a national report covering all 4,296 U.S. data centers is forthcoming.